6.2

Checking

6.2.1

The Actually Zones Checklist Schedule shows all the Zones modelled and their related Elements.

Step 1

Expand the Typology lines so the related Elements are readable. Viewing this allows you to ensure the correct Elements have been associated with the correct Spaces and Typologies.

Note: If a “G” was added as a suffix to the Element IDs of all Elements associated with the garage, all Elements in the related Elements column for the garage Typology should have a “G” at the end.

Note: In the related Elements column for the house Typology only the Interior Walls and Interior Doors that are shared by the garage and house (Unconditioned and Conditioned Typology) should have Element IDs with a “G” suffix.

Step 2

Ensure the Ceilings and Floors are associated with the correct Typologies. If they are not, the Space Boundary Element needs to be adjusted to include these.

Step 3

In the Actually Export Checklist Schedule all Elements can be checked to ensure they have been given appropriate Element IDs and Actually Classifications.